25. Not later than 30 days after the testing has ended and after the end of each testing year if testing takes place over a period of more than one year, a promoter must submit to the Minister and to the Société a report dealing in particular with
(1)  the testing results obtained;
(2)  the duration of the testing for each route;
(3)  the total number of kilometres travelled per automated and manual driving mode;
(4)  the dates of onboard software updates and a summary of the attendant effects on the testing;
(5)  the total number of automated driving mode disengagements and the main reasons for them;
(6)  a summary of traffic accidents;
(7)  the number of mechanical or technological incidents with a description of each and the corrective action taken;
(8)  the number of times the emergency stop was applied;
(9)  the number of complaints received, the subject of the complaints and the measures taken to remedy the situation; and
(10)  any other element considered essential to the monitoring and evaluation of the testing project.
The promoter must also submit the information referred to in the first paragraph on receiving a request to do so from the Minister or the Société.
For the purposes of this section, a testing year begins on the date the testing project is authorized.
M.O. 2018-16, s. 25.
In force: 2018-08-31
25. Not later than 30 days after the testing has ended and after the end of each testing year if testing takes place over a period of more than one year, a promoter must submit to the Minister and to the Société a report dealing in particular with
(1)  the testing results obtained;
(2)  the duration of the testing for each route;
(3)  the total number of kilometres travelled per automated and manual driving mode;
(4)  the dates of onboard software updates and a summary of the attendant effects on the testing;
(5)  the total number of automated driving mode disengagements and the main reasons for them;
(6)  a summary of traffic accidents;
(7)  the number of mechanical or technological incidents with a description of each and the corrective action taken;
(8)  the number of times the emergency stop was applied;
(9)  the number of complaints received, the subject of the complaints and the measures taken to remedy the situation; and
(10)  any other element considered essential to the monitoring and evaluation of the testing project.
The promoter must also submit the information referred to in the first paragraph on receiving a request to do so from the Minister or the Société.
For the purposes of this section, a testing year begins on the date the testing project is authorized.
M.O. 2018-16, s. 25.